May 19, 2024

NE 122ND -B-

Site SheetTOTAL:$13,055.67actual
PersonalHoursCostTOTAL:$1,506.32
Aidan38$645.62
Chris38$860.70
Don – Commison2$0
Labor costs are prelminary
EquipmentHoursCostTOTAL$5,669.90
Blue Dump29$4,054.78
Ford F-3508$164.56
Skid-Steer27$993.33
Mini Track Hoe0$0.00
Large Track Hoe7$325.15
Semi (Tractor)2$114.50
Semi (Trailer)2$17.58
Equipment costs are estimated at this tme based on FEMA Cost codes
MaterialTonsCYcost$5,879.45
Shot Rock82.7559.11$1,572.25
Shot Rock00.00$0.00
1.25″ Special Base49.9535.68$799.20
QTY
48″ x 40′ poly tube1$3,508
materials based on actual invoice prices
40.254382-93.471131