Summary
page shows list of damage to a road due to flooding
Simplified Summary
page shows list of damage to a road due to flooding
SSite | TOTAL: | $6,542.41 | actual | |
Personal | Hours | Cost | TOTAL: | $872.08 |
Aidan | 22 | $373.78 | ||
Chris | 22 | $498.30 | ||
Don – Commison | 0 | $0 | ||
Labor costs are prelminary | ||||
Equipment | Hours | Cost | TOTAL | $2,220.95 |
Blue Dump | 5 | $699.10 | ||
Ford F-350 | 5 | $102.85 | ||
Skid-Steer | 10 | $367.90 | ||
Mini Track Hoe | 13 | $909.74 | ||
Large Track Hoe | 0 | $0.00 | ||
Semi (Tractor) | 0 | $0.00 | ||
Semi (Trailer) | 0 | $0.00 | ||
welding truck | 3 | $141.36 | ||
Equipment costs are estimated at this tme based on FEMA Cost codes | ||||
Material | Tons | CY | cost | $944.86 |
Shot Rock | 34.42 | 24.59 | $653.98 | |
Shot Rock | 0 | 0.00 | $0.00 | |
1.25″ Special Base | 18.18 | 12.99 | $290.88 | |
QTY | ||||
back wall | 1 | $1533.06 | ||
h piling | 2 | $971.46 | ||
materials based on actual invoice prices | ||||
40.054899 | -93.759283 | Completion |